Home » Annan Water Treatment Plant SCADA Upgrade

ANNAN WATER TREATMENT PLANT

 Electrical and SCADA Upgrade

 

This project will increase the reliability of the Cooktown water supply, increase the safety of on-site operators and reduce maintenance costs and outage times.

Location:
Annan Water Treatment Plant. 20 km south of Cooktown.

Scope:
Replacing all of the Electrical cabling on-site, as well as replacing all of the controlling computers and motor controllers.

The design has been completed and a Contractor has been engaged to perform the on-site works

The upgrade includes all of the following:

  • Power cables
  • Switch boards
  • Distribution power boards
  • Motor control centers
  • Cable marshalling panels
  • Supervisory Control and Data Acquisition (SCADA) circuitry
  • Instrumentation cables
  • Plant actuators
  • Industrial Computers, Programmable Logic Controllers, PLC
  • Human Machine Interfaces, HMI
  • Remote Terminal Units used for data collection, RTU
  • Software for the control systems
  • All supporting hardware such as cable ladders and in ground cable trenching.

Budget:
Anticipated Total Project Budget = $2,918,000

 

This project is proudly funded by the Queensland Government through Stage 6 of the Building our Regions ($2,500,000) and the Works for Queensland ($418,000) funding streams.

 

 

1 November 2024: News Story | Annan Water Treatment Plant Upgrade

Project Timeline

  • January 2024
    Construction contract awarded
  • September 2024
    Anticipated on-site works will commence
  • December 2024
    Expected completion