Home » Project Updates » Current Major Projects » 2026-27 Upgrade to seal program

UPGRADE TO SEAL PROGRAM

COOKTOWN & SURROUNDS 2026−27

 

Smoother local roads are on the way, with Cook Shire Council planning bitumen upgrades to 20 selected gravel road sections across Cooktown and surrounding areas.

The program will improve road surfaces in Cooktown, Marton, Endeavour Falls, Keatings Lagoon and Quarantine Bay, helping reduce dust and improve resistance to wet-weather damage.

Location:

Selected road sections across Cooktown, Marton, Endeavour Falls, Keatings Lagoon and Quarantine Bay.

Scope:

Council’s 2026–27 Upgrade to Seal Program will upgrade selected gravel road sections to a two-coat bitumen seal.

The works will:

  • Reduce dust for nearby residents and road users.
  • Provide smoother, longer-lasting road surfaces.
  • Improve resistance to potholes, rutting and erosion.
  • Improve traction for braking.
  • Address drainage and recurring maintenance issues at selected locations.

Crews will prepare and stabilise the road surface, then grade, roll and trim it before applying two layers of bitumen and stone aggregate. Some sections also require roadside clearing, drain shaping or drainage upgrades.

Cooktown

Keatings Lagoon and Quarantine Bay

Marton

Endeavour Falls

Some sections will take longer

Ida Street and Bauhinia Street require water service upgrades before sealing. Tip Access Road requires drainage works, while South Road requires water service and drainage upgrades. These four sections may be delivered later than the main sealing program.

Budgeted at $1,885,500, this program is fully funded through the Australian Government’s Roads to Recovery program.

 

 

 

 

25 November 2026 || Media Release: Smoother roads ahead for Cooktown residents

Project Timeline

Road preparation

Road preparation will be undertaken in stages before bitumen sealing. Some sections require water service or drainage upgrades first.

Bitumen sealing

Late November

Estimated completion

Delivery is targeted for December 2026, subject to weather, resource availability and completion of prerequisite works.

PLEAE NOTE: Some sections requiring water service or drainage upgrades may be delivered later. Confirmed dates will be published as they become available.